Initiatives and Tasks can now be used in equations for calculated metrics, further integrating the Scorecards and Initiatives sections of the software. The following values are available:
- Percent Time Elapsed
- Percent Complete
- Projected Schedule Variance (in days, positive for early)
- Total Budget
- Budget Spent to Date
- Budget Remaining
- Projected Total Budget
- Projected Budget Variance (positive for under budget)
- Projected Budget Variance Percentage (positive for under budget)